Shift Handover
Shift A · R. Iyer → Shift B · R. Sharma · 14:00
Target
6,400pcs
Actual
6,120pcs
Open Issues
3
Safety
Nil
Open Issues
- M203 spindle noise — maintenance scheduled 15:00
- Zinc bath top-up pending on M401
- PPAP revision C sign-off pending for FRG-2048-A
Summary
- Quality
- 1 deviation open on Surface Ra (M501)
- Safety
- Nil incident
- Materials
- Coil CL-99251 low — reorder raised